Phases limited to 10

Excel Help for Phases Limited To 10 in Excel Project Management Template


Forum TopicLogin

Phases Limited To 10

Rate this:
(4/5 from 3 votes)
Surprised Since the phases are limited to 10, we need to create the phase definitions so that tasks can be logically group for the timing. Timing sequence of tasks can be further enforced by applying dependent tasks, and specifying entered start dates which take precedent. After that the participant time resource availability is used. Finally, if all these aspects are equal then the order of the tasks entered is used as time allocated from top to bottom. 